||| FROM JESSE DOUGLAS-SEITZ for SAN JUAN COUNTY PUBLIC WORKS |||


  •  4-day work week, the contractor will work the remainder of the week Tuesday through Friday, with the site open Saturday and Sunday.
  • The Contractor is installing new lateral catch basins, storm drains, and stormwater treatment structures, site grading throughout the project limits to establish road and sidewalk elevations, site survey and staking, and concrete work to form curbs and gutters
  • Full Project Road Closure and Detour 24hr a day during the construction along the Entire Project. The County Contractor will work to restore access to the areas as soon as possible to limit the full road closure. See the temporary traffic closure map.


 

Print Friendly, PDF & Email