On Monday of last week, the School Board opened submitted bids for the 2017 Bond Project. The District received three bids from the following General Contractors: Tiger, Dawson, and Faber Construction. All three bids were in excess of the cost estimates and the Bond Budget. This is not  unusual nor is it unexpected in bidding projects, especially those on the island; however, it means that the projects and overall scope of the bond must be reduced (unfortunately).

During the Special Meeting on Tuesday, the School Board did not accept any of the submitted bids. The Board reviewed and discussed at length the projects within the 2017 Bond and re-prioritized the projects. This will allow the district to issue re-bids to be prepared and advertised this week. Opening of the new bids will take place on Tuesday, December 18.

The new bid package will include the following scope of work for the 2017 Bond:

BASE BID:
Old Gym Renovation
Combination Domestic Water and Fire Pump
Site Access: February 2019
Substantial Completion: August 2019
Field, Base Prep, Curbs, FencingSite Access: April 2019
Substantial Completion: October 2019
ADD ALTERNATES:
Track
Site Access: April 2019
Substantial Completion: October 2019
Multi-Purpose RoomSite Access: January 2019
Substantial Completion: August 2019
Entry Drive, Parking Lot, Pedestrian PathsSite Access: June 2019
Substantial Completion: August 2019

Separate Bid Package

HS Mechanical work will be removed from this bid package and will be bid as a separate package in mid to late January.