From San Juan County Public Works Department

The San Juan County Public Works Department will be replacing the float and wooden pilings and installing handrail on the pier.  Construction is scheduled to begin February 4.  Work is expected to be complete by February 8, weather permitting with expected project completion by February 12.

Expect temporary delays and service during construction.  Public Works and Carlson Construction will work to minimize delays and accommodate facility users as much as possible.  Thank you for your patience as we improve the safety and condition of this important part of our county’s infrastructure.

For more information, contact Dan Vekved, Project Manager at (360) 370-0500 or email: danv@sjcpublicworks.org.