||| FROM JESSIE DOUGLAS-SEITZ, PROJECT MANAGER |||


  • Construction activities are scheduled to begin Monday, March 14, 2022.
  • Traffic Control onsite includes NO PARKING within project limits. This includes Prune Alley, and portions of Fern Street, A Street, and Rose Street. It is essential that areas designated as no parking are unoccupied to allow for planned construction activities including:
    • Mobilization of equipment and materials
    • Construction Surveying
    • Pavement Grinding
  • Please respect temporary traffic control measures, the construction zone speed limit, and directions by our contractor and flagging crew.                                                   

For more information about this project visit our website at: http://www.sanjuanco.com/278/Current-Projects

Prune Alley Traffic Control Map