||| FROM JESSE DOUGLAS SEITZ for SAN JUAN COUNTY PUBLIC WORKS |||


Construction Start Date
T.B.D. Spring 2021

OPALCO Joint Utility Relocation Efforts

The project includes pedestrian and accessibility improvements, transportation infrastructure, storm drain infrastructure, water quality improvements, landscaping, lighting, and consideration for other streetscape amenities.

  • Project Plans have been finalized by the County and are currently being reviewed by WSDOT for approval.
  • The County is expecting to solicit bids for construction this May.
  • The Project Plans currently require the Contractor to complete all subsurface work prior to the upcoming Winter season.
  • The Project Plans also currently provide for a winter suspension of work if the Contractor’s schedule of work and weather conditions require final roadway paving in Spring 2022.
  • Utility relocation efforts, coordinated by OPALCO, including trenching and installation of conduit within the roadway are
    complete.

Thank you for your patience during construction!

For more information about this project visit our website at www.sanjuanco.com/278/Current-Projects.