||| FROM JESSE DOUGLAS-SEITZ for SAN JUAN COUNTY PUBLIC WORKS |||


  • Contractor has shifted to a 4 day work week and plans to leave the road open Friday, Saturday and Sunday for the remainder of the construction season as work permits.
  • Road Closure between Fern Street and A Street for Stormwater main replacement. Road Closure may run 24hr a day.
  • Concrete foundation installation with temporary traffic control throughout site limits all week.
  • OPALCO and Rock Island are on site preparing for the switchover to underground utilities including the removal of overhead lines and poles.
  • Please respect temporary traffic control measures, the construction zone speed limit, directions by our contractor and flagging crews.
  • For your own safety, there is no pedestrians access inside the work zone or areas under road closure.