— from the Orcas Island Library —

Orcas Island Public Library continues expansion project

Framing: The majority of the framing was estimated to be complete last week. Additional miscellaneous areas will be completed in December.

Roof Framing / Sheathing and Water Barrier Installation: Roof sheathing will start on December 5. The roof envelope and underlayment is expected to be completed by December 22. The sheathing will be installed in sections to minimize exposure to weather. The Contractor will secure/fully enclose the building for the week of December 23 holiday through New Year holiday with additional cameras.

Roofing Installation: Scheduled for end of December/January.

Construction Coordination: Submittals ongoing for coordination of scheduled work including casework, etc.