||| FROM SAN JUAN COUNTY COMMUNICATIONS |||
- 4-day work week is anticipated, with the site open Friday, Saturday, and Sunday for the Memorial Day holiday weekend.
- Sewer Switch over, new sewer line and service connections south of A Street will be activated and existing line decommissioned.
- Site demolition is planned, activities may include cutting, pulverizing and hammering for final removal of all existing curb, gutter and sidewalk and roadway pavement.
- Contractor is installing new lateral catch basins, storm drains, and stormwater treatment structures.
- New Road Closure and Detour 24hr a day during the construction along the Entire Project see the temporary traffic closure map.
- North Beach Rd closure south of Enchanted Forest Rd and north of Victory Hill, Prune Alley intersection closed.
- School Road closure west of Pine Street to through traffic, Prune Alley intersection closed.
- Rose Street closure west of Pine Street to through traffic, Prune Alley intersection closed.
- A Street closed between Prune Alley and North Beach Road.
- Prune Alley closed north of Main Street.
- Pedestrian and vehicular access will be limited during pulverization and demolition activities
- Contractor will work to restore access to the areas as soon as possible to limit full road closure
**If you are reading theOrcasonian for free, thank your fellow islanders. If you would like to support theOrcasonian CLICK HERE to set your modestly-priced, voluntary subscription. Otherwise, no worries; we’re happy to share with you.**
Thank you for the weekly updates. The construction is really painful for everyone but it will be beautiful once finished.
Where is the map? Can you provide a link to it here so we don’t have to hunt for it on the county website?
If all the roads are closed, how can we get to the businesses and the school on foot or by car?
Would you please focus on the North Beahc/Prune Alley and School Road intersection first. that is the most well used intersection for anyone coming from the north or west