— from John Van Lund —
dh-bridgeRazz Construction crew members will be working on both the east and west abutments of the bridge replacement project this week. Crews on the west bank will begin driving structural piles at the west abutment cofferdam, as crews on the east bank install Z-piles for the east abutment cofferdam.

Thank you for keeping everyone safe by obeying traffic signals and remaining within areas designated for vehicular and pedestrian traffic.