— from Jesse Douglas-Seitz, San Juan County Project Engineer —

Chipsealing is scheduled for Orcas Hill Road and the Park and Ride on Wednesday 09/06/17 and Thursday 09/07/17. Expect short delays. Flaggers will be on site.

There is no public access or public parking allowed in the Park and Ride site at this time. Please do not enter the site until construction is complete.

Finish grading on Orcas Hill Road and in the Park and Ride is active. Rock retaining walls are complete and the contractor is installing guardrails along the roadway. The log curb parking barrier is complete throughout the site and is constructed from trees harvested on site.

**If it wouldn’t cause you financial distress to take out a modestly-priced, voluntary subscription (HERE), you’d be doing a real service. If it would, then no worries, we’re happy to share with you.**